Wednesday, April 24, 2013
Monday, February 25, 2013
Final Touches to Construction in Progress
Opening is still scheduled for mid-March. The walls are painted, the flooring installed, and it's starting to look very much like a home. Residential Director Phil Errico and architect John Perrin inspect the new lift providing accessibility to the first floor of the house from the garage.
Tuesday, February 12, 2013
Opening Moved to Mid March
Due to the scheduling for the water company to open up the road to connect the line for the fire sprinkler, we've moved the targeted completion date to the second week in March.
Tuesday, January 8, 2013
On target for 2/1 completion!
The first and second floors of the house are ready for paint. The basement ceiling is framed for sheetrock as shown in this picture of Bonnie Brae CEO Bill Powers inspecting the job site.