Thursday, December 27, 2012

Sheetrocking almost done!

The crew worked all weekend and half a day on Christmas eve to get the sheetrock hung and tape and spackle completed.  All necessary inspections have passed.  Trim and doors are next.  Window treatments have been ordered and furniture delivery set.  We are still shooting for early Feb. occupancy.  The project looks great.

Monday, December 3, 2012

Construction Update


The exterior of the house is nearly completed.  The interior rough electric, plumbing, fire, and building inspections are scheduled for this week.  Progress was delayed due to the storm and also due to issues related to the sprinkler system and the Construction Official's understanding of requirements.  We are 2-4 weeks behind the original 1/1/13 move in date.  We are hoping to make up some of that time.