The masonry work for the stair tower providing a second means of egress from all three floors of the house, including the basement, has been completed. Framing is in progress.
The electrician is scheduled to start rough work on Monday. The alarm company and plumber will do their rough work the week after next. The addition should be water tight by next Friday. The job is still on schedule for a 1/1/13 completion.